NSC construction progress as of March 26, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and completing main metal structures of the Arch;
- Assembly of metal structures of tilting panels TP-5-1, TP-5-2, TP-6;
- Assembly of bridging elements of main metal structures of western part of the Arch;
- Completing and assembly of casing girders;
- Assembly of type III tower (temporary structures) for supporting the structures of western end wall;
- Preliminary erection and assembly of steel plating packages for casing, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 13,790.045 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13,284.82 tons

March 26, 2015
March 26, 2015
March 26, 2015
March 26, 2015
March 26, 2015
March 26, 2015