The New Safe Confinement. Construction Chronicle
November 24, 2012, the first lifting of the Arch Eastern part
June 12-14, 2013, the second lifting of the Arch Eastern part
March 31 - April 02, 2014, the skidding of the Arch Eastern part to the waiting area
April 26-27, 2014, the first lifting of the Arch Western part
August 02-03, 2014, the second lifting of the Arch Western part
October 23-24, 2014, the third lifting of the Arch Western part
November 26, 2014, the back skidding of the Arch Eastern part
{flv}news27-11-14_nsc{/flv}
November 14-27, 2016. The Final Movement. Chernobyl NSC Sarcophagus Skidding