NSC construction progress as of November 20, 2014

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Pre-assembling of hinged panels of Eastern part of Arch
- Installation of internal casing;
- Installation of main beams of the casing;
- Dismantling of Arch jacking equipment;
- Dismantling of lifting towers;
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;

- Works on technological building and auxiliary facilities arrangement are underway:
     * Techological building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concreting, concrete curing;
      * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing;
      * firefighting unit access airlocks - delivery and installation of reinforcement cages for a foundation slab.

- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total – 12663,508 tons

Concreting of the Technological building and electrical devices building foundation slab:
Design volume of concrete is – 6542 m3, 6448  m3 is laid (98%) 
Designedy ammount of reinforcement is – 1375 tons, 1333 tons is produced (97,0%)

 