NSC construction progress as of November 06, 2014

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of internal casing;
- Installation of main beams of the casing;
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;
- Works on technological building and auxiliary facilities arrangement are underway:
     * Techological building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concreting, concrete curing, installation of block #8 foundation slab reinforcement of TB (control panel) - completed, concreting of foundation block #8 is scheduled for November 07, 2014  ;
      * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing;
      * firefighting unit access airlocks - delivery and installation of reinforcement cages for a foundation slab.
- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch till 3rd lifting:
Metal structures assembled in total – 12402,649 tons

Concreting of the Technological building and electrical devices building foundation slab:
Design volume of concrete is 6542 m3,  6160  m3 is laid (94%) 
Designedy ammount of reinforcement is – 1375 tons, 1333 tons is produced (97,0%)

 

November 06, 2014
November 06, 2014
November 06, 2014
November 06, 2014
November 06, 2014
November 06, 2014