June 26, 2014

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Installation of bearers for cladding (Western part of the Arch);
- Installation of metal constructions of the northern section of the main cranes system;
- Pre-assembling of the cladding panels;
- Installation of external and internal cladding (western and eastern parts of the Arch);
- Delivery and assembling of galvanized air ducts, preparation for installation and installation of air ducts and supporting structures within the annular space of the Arch western part;
- Arrangement of service zone foundations (southern belt foundation grill reinforcement and concreting);
- Arrangement of the technological building and auxiliary facilities:
     * Technological building - installation of the foundation slab reinforcement (concreting of the second block foundation slab is scheduled on 27.06.2014 (950 m3 of concrete));
     * Fire fighting pump station building - soil grouting;
     * Access gateway for fire brigades - soil grouting.

Assembling of the Arch West part (before 2st jecking):
Metal structures assembled in total – 7,275.606 tons.

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 8,770.7 m3(74.36%); 
Design amount of rebars - 2,447.009 tons, rebar fabrication – 2,246.278 tons (91.8%).

   

June 26, 2014
June 26, 2014
June 26, 2014
June 26, 2014
June 26, 2014
June 26, 2014