Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Installation of girt strip for sheeting (Western part of the Arch);
- sliding ways arrangement;
- Lifting towers Movement;
- Installation of sub-crane beams for main cranes system;
- Assembling of external and internal casing;
- Delivery and assembly of galvanized air ducts, preparation for installation and installation of ducts in the western part of the Arch annular space;
- Arrangement of the service zone foundations (foundation frame of Southern trench);
- Arrangement of engineering building and auxiliary facilities;
- RAW loading and transportation at WDF Buryakovka.
Assembling of the Arch West part (before 2st jecking):
Metal structures assembled in total – 6,794.675 tons.
Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,743.109 tons
Metal structures assembled in total – 12,792.71 tons (93.08%).
Concreting of the Technological building foundation slab:
Design volume of concrete – 6,506 m3, placed – 634.2 m3 (9.8%);
Design amount of rebars - 1,440.2 tons, rebar fabrication – 428.3 tons (29.7%).