Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Installation of girt strip for sheeting (Western part of the Arch);
- Lifting towers Movement;
- Assembling of external and internal casing;
- Delivery and assembly of galvanized air ducts, ducts installation in the annular space of Western part of Arch;
- Arrangement of the service zone foundations (foundation frame of Southern trench);
- Arrangement of engineering building and auxiliary facilities. Technological building ground grouting has been completed.
Assembling of the Arch West part (before 2st jecking):
Metal structures assembled in total – 6,667.624 tons.
Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 7,483.7 m3(63.44%);
Design amount of rebars - 2,447.009 tons, rebar fabrication – 1,973.722 tons (80.66%).