Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Assembling of bearing and hoisting towers;
- Preassembling of cladding panels;
- Arrangement of the service zone foundations (foundation frame of Northern trench);
- Isntallation of CFA piles of service area foundation (Southern trench);
- Arrangement of engineering building and auxiliary facilities.
Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total – 1,865.49 tons (56.14%).
Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,392.5 tons
Metal structures assembled in total – 12,213.31 tons (91.2%).
Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 62 piles (28.7%)