Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Assembling of bearing and hoisting towers (temporary structures for Western part of the Arch);
- Arrangement of the service zone foundations;
- Arrangement of engineering building and auxiliary facilities.
Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total – 1,535.26 tons (46.2%).