September 05, 2013

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- preliminary assembling of panels of Arch metal structures;
- setting-up of equipment for the 3rd lifting;
- assembling of purlines for cladding;
- assembling of inner and outer cladding of the Arch;
- reinforcement and concreting of Service Zone’s ground beam (the Northern trench);
- installation of a base plate for pile field of Service Zone’s foundation (the Southern trench);
- works on installation of the technological building and auxiliary facilities.

Assembling of metal structures of the Arch (till Lifting No.3)
Under design - 2286 tons, performed - 672.83 tons (29.43%)

Arch Ground Beam in the Transfer Zone:
Concrete: under design - 7677.6 m3, placed - 6561.5 m3 (85.46%); 
Reinforcing steel: under design - 1593.128 tons, manufactured - 1504.940 tons (94.4%)

Arrangement of foundations in the Arch’s serviced area (northern slip):
Concrete: under design - 5,674.2 m3, placed - 2,265.0 m3 (39.92%); 
Reinforcing steel: under design - 1198,678 tons, manufactured - 826,455.0 tons (88.95%)