Within the NSC Project at the construction site the following works are being performed:
- Preliminary assembling of the Arch metal structure panels;
- Assembling of the Arch metal structures;
- Installation of casing girders;
- Assembling of external and internal casing of the Arch;
- Reinforcing and concreting the foundation frame of the serviced area (northern trench);
- Activities on arranging an engineering building and auxiliary facilities.
Assembling of metal structures of the Arch (till Lifting No.3)
Under design - 2286 tons, performed - 460.88 tons (20.12%)
Arrangement of foundations in the Arch’s serviced area (northern slip):
Concrete: under design - 5,674.2 m3, placed - 1290 m3 (22.73%);
Reinforcing steel: under design - 1198,678 tons, manufactured - 722,749 tons (60.29%)