Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling of panels of metal structures of the Arch;
- Installation of girders for casing;
- Dismantling of jacking system containers;
- Displacement of lifting towers;
- Assembling of external and internal casing of the Arch;
- Reinforcement and concreting of the serviced area ground beam (northern slip);
- Operations on arranging an engineering building and auxiliary structures.
Assembling of metal structures of the Arch (till Lifting No.3)
Under design - 2286 tons, performed - 290.26 tons (12.69%)
Arrangement of foundations in the Arch’s serviced area (northern slip):
Concrete: under design - 5,674.2 m3, placed - 686 m3 (12.10%);
Reinforcing steel: under design - 1,251.609 tons, manufactured - 452.428 tons (36.15%)