July 25, 2013

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Assembling of metal structures of eastern end wall of the Arch;
- Installation of girders for internal casing;
- Preparation for displacement of lifting towers;
- Assembling of external casing of the Arch (eastern end wall);
- Arrangement of inclined piles in the serviced area (northern slip foundations);
- Reinforcement of the serviced area foundation (northern slip);

Assembling of metal structures of the Arch (till Lifting No.3)
 Under design – 2,286 tons, performed – 247.2 tons (10.8%)

Arrangement of foundations in the Arch’s serviced area (northern slip):
Concrete: under design – 5,674.2 m3; placed – 467 m3 (8.23%);
Reinforcing steel: under design – 1,251.609 tons; manufactured – 416.684 tons (33.29%).

Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 1,058 m3 (99.81%);
- Design pile amount – 208 piles, placed till design mark – 208 piles (100%)