During the first half of August 04, 2016 at ISF-2 construction site the following works were carried out:
Spent Fuel Processing Facility (SFPF):
- Mounting of cable routing structures within SFPF building premises;
- Cable routing within SFPF building premises;
- Installation of SFPF building lighting system;
- Installation of self-leveling floors in SFPF premises;
- Laying of active drainage pipes of LRW system;
- Pipe laying of RAW level monitoring tanks;
- Installation of gates MIS-LD-04 in premise 114/119 of SFPF building;
- Installation of gates MIS-LD-0 in premise 107 of SFPF building;
- Installation of doors Tornado in SFPF building;
- Mounting of utility air compressors;
- Corrosion protection and pipe covering of cold supply system;
- Installation of diesel generators in the designed position;
- Electrical fitting works relating to DPP (cabinet wiring, power cabling).
Concrete storage modules (CSM):
- Installation of imbedded items for CSM temperature monitoring.
The following activities were also performed at the facility:
- Laying of distribution mains from automatic load transfer cabinets to technical security equipment consumers;
- Twisted pair cabling from transducer locations to physical protection system (PPS) cabinets;
- Remounting of physical protection system (PPS) safety gates – installation of new gate foundations from Check Point side.
The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 186 people at the total were engaged in work performance. 6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.