During the first half of August 04, 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Mounting of cable routing structures within SFPF building premises;
- Cable routing within SFPF building premises;
- Installation of SFPF building lighting system;
- Installation of self-leveling floors in SFPF premises;
- Laying of active drainage pipes of LRW system;
- Pipe laying of RAW level monitoring tanks;
- Installation of gates MIS-LD-04 in premise 114/119 of SFPF building;
- Installation of gates MIS-LD-0 in premise 107 of SFPF building;
- Installation of doors Tornado in SFPF building;
- Mounting of utility air compressors;
- Corrosion protection and pipe covering of cold supply system;
- Installation of diesel generators in the designed position;
- Electrical fitting works relating to DPP (cabinet wiring, power cabling).

Concrete storage modules (CSM):
- Installation of imbedded items for CSM temperature monitoring.

The following activities were also performed at the facility:
- Laying of distribution mains from automatic load transfer cabinets to technical security equipment consumers;
- Twisted pair cabling from transducer locations to physical protection system (PPS) cabinets;
- Remounting of physical protection system (PPS) safety gates – installation of new gate foundations from Check Point side.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 186 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

August 04, 2016
August 04, 2016
August 04, 2016
August 04, 2016
August 04, 2016
August 04, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Supply of metal structures to the site;
- Mounting of hydraulic jacks for the Arch sliding;
- Installation of special doors of the Arch;
- Installation of sealing membrane of tilting panels;
- Installation of cable routes for control and measuring instruments of North and South Ventilation Centers;
- Installation of protective shielding of North Garage;
- Installation of external and internal cladding;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment);
- Start of delivering the NSC’s ventilation stack elements.

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* MCS temporary control board installed. Adjusting the control system.

- Erection of 25t crane for MCS maintenance garage:
* Installation of electrical crane equipment.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, filling with putty and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes for fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof water isolation, installation of pipelines for fire-preventive and drinking water supply, laying electrical cables;
* Fire pump station (FPS) – works relating to pre-coating, filling with putty and painting of walls inside the building;
* Site of diesel power plant for power supply – laying electrical cables and connecting diesel generators.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water collecting basins;
* Construction of roads in the Local Zone.

Erection of Arch western part steelwork:
Erected in total
– 15,931.41 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

July 28, 2016
July 28, 2016
July 28, 2016
July 28, 2016
July 28, 2016
July 28, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Supply of metal structures to the site;
- Supply of hydraulic jacks to the site for the Arch sliding;
- Installation of special doors of the Arch;
- Installation of sealing membrane of tilting panels;
- Installation of cable routes for control and measuring instruments of North and South Ventilation Centers;
- Installation of protective shielding of North Garage;
- Installation of external and internal cladding. Total progress – 98%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress – 88 %;

Main Cranes System (MCS) installation:

- Adjusting the crane beams and rails;
- Preparing the MCS bridges for rerolling to west side of the Arch;
- Preparing for mounting a bottom platform of a mobile tool platform (MTP) – completed;
- Installation of MCS control boards for subsequent testing the crane.

- Erection of 25t crane for MCS maintenance garage:
* Installation of electrical crane equipment.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, filling with putty and painting of walls and ceilings inside the building, installation of doors. Progress (construction part – 93%);
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes for fire-preventive and drinking water supply. Progress (construction part) – 100%;
* Access gateway for fire brigades – roof water isolation, installation of pipelines for fire-preventive and drinking water supply, laying electrical cables;
* Fire pump station (FPS) – works relating to pre-coating, filling with putty and painting of walls inside the building;
* Site of diesel power plant for power supply – laying electrical cables and connecting diesel generators.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water collecting basins;
* Construction of roads in the Local Zone.

Erection of Arch western part steelwork:
Erected in total
– 15,917.11 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016

Select another date

During the first half of July 21, 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Cable routing within building premises;
- Installation of self-leveling floors;
- Installation of lighting system;
- Laying of active drainage pipes of LRW system;
- Pipe laying of RAW level monitoring tanks;
- Installation of basic process equipment – installation of sliding holder frame SFP CR 220 in the designed position is completed in premise 501 of SFPF building. Following the acceptance, the BNG representatives will restore mounting/installation activities;
- Installation of gates MIS-LD-04 in premise 114;
- Preparatory works for mounting of ventilation system equipment.

Concrete storage modules (CSM):

- Installation of lightning protection on modules;
- Installation of imbedded items for CSM temperature monitoring;
- Mounting of ventilation grills is completed.

The following activities were also performed at the facility:

- Laying of distribution mains from automatic load transfer cabinets to technical security equipment consumers;
- Remounting of physical protection system (PPS) safety gates – installation of new gate foundations from Check Point side;
- Twisted pair cabling from transducer locations to physical protection system (PPS) cabinets.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 196 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016
July 21, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of special doors of the Arch;
- Adjustment of automated jacks of tilting panels TP-5.1, TP-5.2, TP-6;
- Installation of tilting panels sealing membrane;
- Installation of cable routes for control and instrumentation of Northern and Southern Ventilation Centres;
- Installation of Northern garage protective shielding;
- Installation of external and internal cladding. Overall progress – 96%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding, preparation of NVC for vent systems installation. Progress – 88%

- Main Cranes System (MCS) installation:

* Final leveling of crane-runway girders;
* Cutting and installation of tracks.

- 25t crane for MCS Maintenance garage:

* Reassembly of crane;
* Final leveling of crane-runway girders and installation of tracks (works completed).

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – installation of reinforcement cages and formwork of walls, and heat insulation of roof. Overall progress (construction part) – 93%;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays,  cable layout, heat insulation of roof. Progress (construction part) – 100%;
* Fire Subdivision Access Lock (FSAL) – finishing of the building and heat insulation of roof;
* Firewater pumping station (FWR) – construction works completed. Finishing of the building and heat insulation of roof. 

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,906.47 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t