Within the NSC Project at the construction site the following works are being performed:
- Delivery of tertiary steel structures to the site;
- Mounting of hydraulic jacks for Arch sliding;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- installation of sealing membrane anchors along the end wall
- Installation of special doors of the Arch;
- Installation of sealing membrane of swing panels;
- Installation of protective shielding of North Garage;
- Pre-assembling and mounting of rolling doors of North Garage;
- Installation of external and internal casing. Progress - 98%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 91%;
- preparation for installation and welding of Arch ventilation stack elements.

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* Adjusting and connecting MCS control panels.

- 25t crane for MCS Maintenance garage:
* Completion of crane installation.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 97%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators, installation of equipment.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone - 25.7%.

Erection of Arch western part steelwork:
Erected in total
– 15,951.41 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

August 18, 2016
August 18, 2016
August 18, 2016
August 18, 2016
August 18, 2016
August 18, 2016

Select another date

During the first half of August 18, 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Development of work execution plans (flow diagrams) for installation of equipment and systems;
- Mounting of cable routing structures within SFPF building premises;
- Cable routing within SFPF building premises;
- Installation of SFPF building lighting system;
- Installation of self-leveling floors in SFPF premises;
- Laying of active drainage pipes of LRW system;
- Pipe laying of RAW level monitoring tanks;
- Installation of gates MIS-LD-04 in premise 114/119 of SFPF building;
- Installation of gates MIS-LD-0 in premise 107 of SFPF building;
- Installation of doors Tornado in SFPF building;
- Installation of pipelines (pipework) for compressors of compressed air system;
- Corrosion protection and pipe covering of cold supply system;
- Installation of equipment for ventilation systems;
- Installation of main process equipment – welding works on lifting device for SFP-TD-211S;
- Electrical fitting works relating to DPP (cabinet wiring, power cabling).

Concrete storage modules (CSM):
- Installation of imbedded items for CSM temperature monitoring.

The following activities were also performed at the facility:
- Twisted pair cabling from transducer locations to physical protection system (PPS) cabinets;
- Routing of optic cable along the perimeter of PPS;
- Reinstallation of PPS security gates – construction of new foundations from the direction of Gate House;
- Development of testing programs for process units and systems.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 179 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

Select another date

During the first half of August 11, 2016 at ISF-2 construction site the following works were carried out:

Spent Fuel Processing Facility (SFPF):
- Mounting of cable routing structures within SFPF building premises;
- Cable routing within SFPF building premises;
- Installation of SFPF building lighting system;
- Installation of self-leveling floors in SFPF premises;
- Laying of active drainage pipes of LRW system;
- Pipe laying of RAW level monitoring tanks;
- Installation of gates MIS-LD-04 in premise 114/119 of SFPF building;
- Installation of gates MIS-LD-0 in premise 107 of SFPF building;
- Installation of doors Tornado in SFPF building;
- Installation of pipelines (pipework) for compressors of compressed air system;
- Corrosion protection and pipe covering of cold supply system;
- Start of ventilation system equipment installation Renewal of installation of process equipment – welding activities on lifting device for SFP-TD-211;
- Electrical fitting works relating to DPP (cabinet wiring, power cabling).

Concrete storage modules (CSM):
- Installation of imbedded items for CSM temperature monitoring.

The following activities were also performed at the facility:
- Twisted pair cabling from transducer locations to physical protection system (PPS) cabinets;
- Routing of optic cable along the perimeter of PPS;
- Reinstallation of PPS security gates – construction of new foundations from the direction of Gate House;
- Development of testing programs for process units and systems.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 186 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

August 11, 2016
August 11, 2016
August 11, 2016
August 11, 2016
August 11, 2016
August 11, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Supply of metal structures to the site;
- Mounting of hydraulic jacks for Arch sliding;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- installation of sealing membrane anchors along the end wall
- Installation of special doors of the Arch;
- Installation of sealing membrane of swing panels;
- Installation of protective shielding of North Garage;
- Pre-assembling and mounting of rolling doors of North Garage;
- Installation of external and internal casing. Progress - 98%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 91%;
- preparation for installation and welding of Arch ventilation stack elements.

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* Adjusting and connecting MCS control panels.

- 25t crane for MCS Maintenance garage:
* Installation of electrical crane equipment.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 97%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators, installation of equipment.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone - 23,5%.

Erection of Arch western part steelwork:
Erected in total
– 15,951.41 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

August 11, 2016
August 11, 2016
August 11, 2016
August 11, 2016
August 11, 2016
August 11, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Supply of metal structures to the site;
- Mounting of hydraulic jacks for Arch sliding;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- Installation of special doors of the Arch;
- Installation of sealing membrane of swing panels;
- Installation of protective shielding of North Garage;
- Pre-assembling and mounting of rolling doors of North Garage;
- Installation of external and internal casing;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment).

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* Adjusting and connecting MCS control panels.

- 25t crane for MCS Maintenance garage:
* Installation of electrical crane equipment.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork:
Erected in total
– 15,943.61 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t