Within the NSC Project at the construction site the following works are being performed:

- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of East End wall;
- installation of sealing anchors on ASRC roof;
- installation of special doors of the Arch;
- installation of protective shielding of North garage and runways;
- installation of external and internal cladding. Progress - 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 92%;
- the main part of the NSC ventilation stack was erected. The erection works are in progress.

- Main Cranes System (MCS) installation:

* the East and West bridges were moved to the Arch western half;
* Alignment and connection of control panels to MCS, training of personnel and testing of systems.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 98.4%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Fire Units Access Lock – polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors; installation of network systems inside the building.
* Fire pump station (FPS) – works on pre-coating, coating and painting of walls inside the building, installation of equipment; installation of the northern firewater tank is coming to an end, preparation for installation of the southern tank.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch end walls;
* Construction of roads in Local zone - 29%.

Erection of Arch western part steelwork:

Erected in total – 16,061.62 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

September 15, 2016
September 15, 2016
September 15, 2016
September 15, 2016
September 15, 2016
September 15, 2016

 

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of tertiary steel structures to the site;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- Installation of anchors of East End wall;
- installation of sealing anchors on ASRU roof;
- installation of special doors of the Arch;
- installation of steel support structures of Ventilation stack;
- installation of protective shielding of North garage and runways;
- Installation of external and internal casing. Progress - 99%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 91%;
- Welding of Arch Ventilation stack units. Pre-assembly of Ventilation stack maintenance sites.

- Main Cranes System (MCS) installation:

* Start of the procedure on moving MCS bridges to the Arch western half;
*
Alignment and connection of control panels to MCS, training of personnel and testing of systems.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 98%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Fire Subdivisions Access Lock (FSAL) – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building, installation of northern firewater tank;

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone - 28.2%.

Erection of Arch western part steelwork:

Erected in total – 16,045.01 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016

 

Select another date

Spent Fuel Processing Facility (SFPF):

- Development of work execution plans (process charts) for installation of equipment and systems.
- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within the SFPF building premises.
- Installation of SFPF building lighting system.
- Installation of self-leveling floors in the SFPF premises.
- Installation of pipelines for LRW active drain system.
- Installation of pipelines for nitrogen supply system.
- Installation of pipelines for argon supply system.
- Installation of pipelines for helium supply system.
- Gate MIS-LD-04 was installed in the prem. 114/119 of SFPF building.
- Gate MIS-LD-0 was installed in prem. 107 of SFPF building.
- Doors Tornado was installed in the SFPF building.
- Installation of pipelines (pipework) for compressors of compressed air system.
- Installation of main process equipment – welding works on a lifting device for SFP TP-TD-211.
- Installation of main process equipment – welding works on a slide holder supporting frame SFP-CR-220.
- Installation of main process equipment – installation of a sliding door leaf safety SFP-SD-212 in the prem. 111B/312 into the design position.
- Installation of main process equipment – a sliding safety door leaf SFP-SD-211 was installed in the prem. 307B/305 into the design position, installation of drive system and other small elements.
- Installation of main process equipment – preparation of an air-tight door frame SFP SD 240 for installation (prem. 501/503).
- Installation of main process equipment – installation of floor (Rased Floor) of Caisson 501A MIS-CE-213.
- Installation of main process equipment – installation of transport trolley rails SWP-TD-222 into the design position (prem. IS102C6 / 403).
- Installation of equipment – prem. 705, level 21,300. Ventilation systems CAVS-S-CAVS 1 and-2.
- Installation of air ducts, level 21,300. Ventilation systems CAVS-S-CAVS 1 and-2.
- Installation of cold supply control system units – prem. 405 (connection to system CAVS-S-1).
- Installation of internal protective grounding of SFPF building.
- Making a wider door opening of the prem. 132 of SFPF building.
- Brickwork of partition in the prem. 105/137 of SFPF building.
- Electrical installation works on a diesel power plant (DPP) – installation of control cables.Concrete storage modules (CSM):
- Installation of imbedded items for CSM temperature monitoring.

Concrete storage modules (CSM):

- Lightning protection (lighting-conductor) was installed at CSM modules.
- Installation of embedded items for the CSM temperature control.
- Drilling holes for boroscopes at CSM modules.

The following activities were also performed at the facility:

- Laying of optic cable from the protective tube unit (PTU) to Control Panel 1 along the PPS perimeter.
- Construction of foundations for PPS video camera supports.
- Concreting of joining along guard duty paths.
- Packing up a set of as-built documents and deliverables for delivery of the relevant phases in accordance with the Contract.
- Development of testing programs for process units and systems.
- Tests of process units and systems – hydraulic tests of chemically demineralized water system.

The general Сontractor of the project is Holtec Company. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. 167 people at the total were engaged in work performance.  6 units of earth-moving machinery, lorry, and lifting machines were used for implementing tasks at the site.

September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery of tertiary steel structures to the site;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- installation of sealing membrane anchors along the end wall
- Installation of special doors of the Arch;
- Installation of sealing membrane of swing panels;
- Installation of protective shielding of North Garage;
- Pre-assembling and mounting of rolling doors of North Garage;
- Installation of external and internal casing. Progress - 99%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 91%;
- Welding of Arch Ventilation stack units. Pre-assembly of Ventilation stack maintenance sites.

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* Adjusting and connecting MCS control panels.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 98%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators, installation of equipment.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone - 28%.

Erection of Arch western part steelwork:
Erected in total
– 16,019.88 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t

 

Select another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery of tertiary steel structures to the site;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- installation of sealing membrane anchors along the end wall
- Installation of special doors of the Arch;
- Installation of sealing membrane of swing panels;
- Installation of protective shielding of North Garage;
- Pre-assembling and mounting of rolling doors of North Garage;
- Installation of external and internal casing. Progress - 98%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 91%;
- Welding of Arch Ventilation stack units. Pre-assembly of Ventilation stack maintenance sites.

- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* Adjusting and connecting MCS control panels.

- 25t crane for MCS Maintenance garage:
* Completion of crane installation.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 97%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators, installation of equipment.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone - 26%.

Erection of Arch western part steelwork:
Erected in total
– 15,964.28 t

Erection of Arch eastern part steelwork:
Erected in total
– 14,265.62 t