Within the NSC Project at the construction site the following works are being performed:
- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of East End wall;
- installation of sealing anchors on ASRC roof;
- installation of special doors of the Arch;
- installation of protective shielding of North garage and runways;
- installation of external and internal cladding. Progress - 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 92%;
- the main part of the NSC ventilation stack was erected. The erection works are in progress.
- Main Cranes System (MCS) installation:
* the East and West bridges were moved to the Arch western half;
* Alignment and connection of control panels to MCS, training of personnel and testing of systems.
- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 98.4%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Fire Units Access Lock – polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors; installation of network systems inside the building.
* Fire pump station (FPS) – works on pre-coating, coating and painting of walls inside the building, installation of equipment; installation of the northern firewater tank is coming to an end, preparation for installation of the southern tank.
- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch end walls;
* Construction of roads in Local zone - 29%.
Erection of Arch western part steelwork:
Erected in total – 16,061.62 t
Erection of Arch eastern part steelwork:
Erected in total – 14,265.62 t