Spent Fuel Processing Facility (SFPF):

- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within the SFPF building premises.
- Installation of SFPF building lighting system – modification of cable routing at stair flights according to the fire safety requirements.
- Installation of self-leveling floors in premises.
- Installation of main process equipment:
     * Installation of Caisson 501A MIS-CE-213 (welding works).
     * Installation of SWP-TD-222 transport trolley rails into the design position (prem. IS102C6 / 403) was completed. Handed over for concreting.
     * Installation of security door SFP SD 210 (prem. 501А/IS102c2).
- Installation of internal protective grounding of SFPF building.
- Installation of radiation monitoring system — mounting of cable routing and earthquake-resistant supporting brackets for equipment, installation of devices into the SFPF premises.
- Installation of spill-over tanks.
- Preparatory works for installation of forced gas dehydration (FGD) pipelines.

Concrete storage modules (CSM):

- Installation of embedded items for the CSM temperature control was completed.
- Drilling of holes for boroscopes at the CSM modules (drilled 364 out of 464 holes).

The following activities were also performed at the facility:

- Development of work execution plans (process charts) for installation of equipment and systems.
- Construction of foundations for supports of physical protection system (PPS) video cameras was completed.
- Installation of racks (supports) for the PPS video cameras.
- Installation of tube protection blocks along the PPS perimeter.
- Installation of sensors along the PPS perimeter.
- Installation of PPS security gate near the Check Point (ChP).
- Repair of corrosion-resistant coating of PPS gate.
- Installation of portal monitors for dosimetry control system.
- Installation of access control system (turnstile) at the ChP gatehouse.
- Packing up a set of as-built documents and deliverables to deliver the relevant phases in accordance with the Contract.
- Development of testing programs for process units and systems.
- Development of training programs for the Client’s personnel.


The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 178 persons were engaged in the works, as well as 4 units of lorry and lifting machines.

Select another date

Within the NSC Project at the construction site the following works are being performed:

- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of East End wall; 
- installation of sealing anchors at the north-east; 
- installation of special doors of the Arch; 
- installation of protective shielding of North garage and runways;
- installation completion of external and internal cladding. Progress - 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 98%;
- erection of the NSC ventilation stack was completed.

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* alignment and connection of control panels to the MCS, testing of control systems.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TB) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures.  Progress (construction part) - 99.6%.
* Electrical Equipment Building (EEB) – installation of fire alarm system and lighting within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures. Mounting of the frame metal structures for the EEB face heat insulation and lining.  
* Fire Units Access Lock – polishing, pre-coating, coating and painting of walls and ceilings inside the building. 
* Fire pump station (FPS) –installation of the southern fire water tank. Arrangement of face heat insulation and lining.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch end walls;
* Construction of roads in Local zone - 30%.

Erection of Arch western part steelwork:

Erected in total – 16,104.10 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

October 07, 2016
October 07, 2016
October 07, 2016
October 07, 2016
October 07, 2016
October 07, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of East End wall;
- installation of sealing anchors at the north-east;
- installation of special doors of the Arch;
- installation of protective shielding of North garage and runways;
- installation of external and internal cladding. Progress - 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 92%;
- erection of the NSC ventilation stack was completed.

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* alignment and connection of control panels to the MCS, testing of control systems.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TB) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures.  Progress (construction part) - 99.6%.
* Electrical Equipment Building (EEB) – installation of fire alarm system and lighting within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures. Mounting of the frame metal structures for the EEB face heat insulation and lining. 
* Fire Units Access Lock – polishing, pre-coating, coating and painting of walls and ceilings inside the building.
* Fire pump station (FPS) –installation of the southern fire water tank. Arrangement of face heat insulation and lining.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch end walls;
* Construction of roads in Local zone - 29%.

Erection of Arch western part steelwork:

Erected in total – 16,094.80 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016

Select another date

Spent Fuel Processing Facility (SFPF):

- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within the SFPF building premises.
- Installation of SFPF building lighting system.
- Installation of self-leveling floors in the SFPF premises.
- Installation of pipelines for LRW active drain system.
- Installation of pipelines for nitrogen supply system.
- Installation of pipelines for argon supply system.
- Installation of pipelines for helium supply system.
- Installation of main process equipment:
     * Installation of lifting device system for ТП SFP-TD-211 was completed, the equipment is ready for individual tests.
     * Installation of air-tight door SFP SD 240 (prem. 501/503) was completed.
     * Installation of Caisson 501A MIS-CE-213 upper part.
     * Installation of transport trolley rails SWP-TD-222 into the design position (prem. IS102C6 / 403).
Installation of cold supply control system units – prem. 405 (connection to system CAVS-S-1).
Installation of internal protective grounding of SFPF building.
Installation of radiation monitoring system – drilling of holes for installation of devices, mounting of cable routing and earthquake-resistant supporting brackets for equipment.

Concrete storage modules (CSM):

- Installation of embedded items for the CSM temperature control was completed.
- Drilling of holes for boroscopes at the CSM modules (drilled 220 out of 464 holes).

The following activities were also performed at the facility:

- Laying of optic cable along the PPS perimeter.
- Construction of foundations for PPS video cameras supports.
- Concreting of joining along guard duty paths.
-  Development of work execution plans (process charts) for installation of equipment and systems.
- Packing up a set of as-built documents and deliverables to deliver the relevant phases in accordance with the Contract.
- Development of testing programs for process units and systems.
- Tests of process units and systems – hydraulic tests of chemically demineralized water system.
- Development of training programs for the Client’s personnel.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 193 persons were engaged in the works. 4 units of earth-moving machinery, lorry and lifting machines were used for implementing the tasks at the site.

September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of East End wall;
- installation of sealing anchors on ASRC roof;
- installation of special doors of the Arch;
- installation of protective shielding of North garage and runways;
- installation of external and internal cladding. Progress - 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 92%;
- the main part of the NSC ventilation stack was erected. The erection works are in progress.

- Main Cranes System (MCS) installation:

* the East and West bridges were moved to the Arch western half;
* Alignment and connection of control panels to MCS, training of personnel and testing of systems.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 98.56%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Fire Units Access Lock – polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors; installation of network systems inside the building.
* Fire pump station (FPS) – works on pre-coating, coating and painting of walls inside the building, installation of equipment; installation of the northern firewater tank is coming to an end, preparation for installation of the southern tank.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch end walls;
* Construction of roads in Local zone - 29%.

Erection of Arch western part steelwork:

Erected in total – 16,070.62 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t