Within the NSC Project at the construction site the following works are being performed:

- Delivery of tertiary steel structures to the site;
- Installation of sliding system control module, inspection and installation of the Arch sliding equipment;
- Installation of anchors of East End wall;
- Installation of sealing anchors at the south-east and at the western end of Deaerator Stack and turbine hall;
- Installation of special doors of the Arch;
- Installation of protective shielding of Northern garage and runways;
- Completion of external and internal cladding installation; works on testing the sealing capacity of the cladding. Progress – 99 %;
- Ventilation system (installation of air ducts is near completion, works have been started on installing ventilation equipment);

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* preparation for MCS testing.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works on polishing, priming, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures.  Progress (construction part) — 98.7%;
* Electrical Equipment Building (EEB) – installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for heat insulation of walls and facing of EEB facade;
* Fire Subdivisions Access Lock (FSAL) – polishing, priming, coating and painting of walls and ceilings inside the building;
* Fire water pumping station (FPS) – heat insulation of walls and facing of facade.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 33%.

Erection of Arch western part steelwork:

Erected in total – 16,136.44 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of tertiary steel structures to the site;
- Installation of sliding system control module, inspection and installation of the Arch sliding equipment;
- Installation of anchors of East End wall;
- Installation of sealing anchors at the south-east and at the western end of Deaerator Stack and turbine hall;
- Installation of special doors of the Arch;
- Installation of protective shielding of Northern garage and runways;
- Completion of external and internal cladding installation; works on testing the sealing capacity of the cladding. Progress – 99 %;
- Ventilation system (installation of air ducts is near completion, works have been started on installing ventilation equipment);

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* alignment and connection of control panels to the MCS, testing of control systems;
* Preparation for MCS testing.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works on polishing, priming, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures.  Progress (construction part) — 98.7%;
* Electrical Equipment Building (EEB) – installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for heat insulation of walls and facing of EEB facade;
* Fire Subdivisions Access Lock (FSAL) – polishing, priming, coating and painting of walls and ceilings inside the building;
* Fire water pumping station (FPS) – heat insulation of walls and facing of facade.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 32%.

Erection of Arch western part steelwork:

Erected in total – 16,126.44 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

October 27, 2016
October 27, 2016
October 27, 2016
October 27, 2016
October 27, 2016
October 27, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of tertiary steel structures to the site;
- Installation of sliding system control module, inspection and installation of the Arch sliding equipment;
- Installation of anchors of East End wall; 
- Installation of sealing anchors at the north-east was completed;
- Installation of sealing anchors at the south-east and at the western end of deaerator stack, and turbine hall;
- Installation of special doors of the Arch; 
- Installation of protective shielding of Northern garage and runways;
- Completion of external and internal cladding installation; works on testing the sealing capacity of the cladding. Progress – 99 %;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress – 98%;
- Completion of NSC ventilation stack installation;

- Main Cranes System (MCS) installation:

* Adjustment of crane-runway girders and rails;
* Alignment and connection of control panels to the MCS, testing of control systems.
* Preparation to MCS testing;
* Testing of 25-t crane for MCS Maintenance garage.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works on polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures.  Progress (construction part) – 98,6%;
* Electrical Equipment Building (EEB) – installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for heat insulation of walls and facing of EEB facade;
* Fire Subdivisions Access Lock (FSAL) – polishing, pre-coating, coating and painting of walls and ceilings inside the building;
* Fire pumping station (FPS) – leak testing of tanks. Heat insulation of walls and facing of facade.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 32%.

Erection of Arch western part steelwork:

Erected in total – 16,119.20 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

Select another date

Spent Fuel Processing Facility (SFPF):

- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within premises.
- Installation of SFPF building lighting system — modification of cable routing at stair flights according to the fire safety requirements.
- Installation of self-leveling floors in premises.
- Installation of main process equipment:
     * Installation of security door SFP SD 210 (prem. 501А/IS102c2).
     * Installation of security door SFP SD 212 (prem. 312B).
     * Installation of security door SFP SD 211 (prem. 307).
- Preparatory works for installation of shielding windows.
- Installation of internal protective grounding of SFPF building.
- Installation of radiation monitoring system — mounting of radiological monitors in the SFPF premises.

Concrete storage modules (CSM):

- Drilling of 464 holes for borescopes at the modules complete.
- Installation of embedded items for borescopes at the modules.

The following activities were also performed at the facility:

- Development of work execution plans (process charts) for installation of equipment and systems.
- Installation of tube protection blocks along the physical protection system (PPS) perimeter complete.
- Installation of sensors along the PPS perimeter.
- Installation of supports for the PPS video cameras at the SFPF building.
- Installation of PPS security gate near the Check Point (ChP) — installation of gate leaf into its design position.
- Installation of PPS security gate near the SFPF — installation of gate leaf into its design position.
- Repair of corrosion-resistant coating of PPS gate.
- Installation of portal monitors for dosimetry control system.
- Installation of access control system (turnstile) at the ChP gatehouse.
- Packing up a set of as-built documents and deliverables to deliver the relevant phases in accordance with the Contract.
- Development of testing programs for process units and systems.
- Development of training programs for the Client’s personnel.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 182 persons were engaged in the works, as well as 5 units of earth-moving, lorry and lifting machines.

October 20, 2016
October 20, 2016
October 20, 2016
October 20, 2016
October 20, 2016
October 20, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and installation of the Arch sliding equipment;
- Installation of anchors of East End wall; 
- installation of sealing anchors at the north-east; 
- installation of special doors of the Arch; 
- installation of protective shielding of North garage and runways;
- installation completion of external and internal cladding. Progress — 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress — 98%;
- erection of the NSC ventilation stack was completed.
- installation of sealing anchors.

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* alignment and connection of control panels to the MCS, testing of control systems;
* Testing of 25-t crane.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TB) — works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures.  Progress (construction part) — 99.6%.
* Electrical Equipment Building (EEB) — installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for heat insulation of walls and facing of EEB facade.  
* Fire Units Access Lock (FSAL) — polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors. Installation of utilities inside the building. 
* Fire pump station (FPS) — installation of southern fire water tank. Heat insulation and facing.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 32%.

Erection of Arch western part steelwork:

Erected in total – 16,108.57 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t