Within the NSC Project at the construction site the following works are being performed:
- Preparatory activities before the sliding;
- Delivery of tertiary steel structures to the site;
- Inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of West End wall;
- Installation of sealing anchors;
- Installation of special doors of the Arch;
- Installation of protective shielding of North garage and runways;
- Completion of external and internal cladding installation; works on testing the sealing capacity of the cladding. Progress — 99 %;
- Ventilation system (installation of air ducts is at completion stage, installation of ventilation equipment);
- Main Cranes System (MCS) installation:
* Adjustment of crane-runway girders uipment;
* Testing of MCS (static and dynamic load).
- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) — works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures. Installation of the building face. Progress (construction part) — 98.7%;
* Electrical Equipment Building (EEB) — installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for the face heat insulation and lining;
* Fire Subdivisions Access Lock (FSAL) — polishing, priming, coating and painting of walls and ceilings inside the building;
* Fire water pumping station (FPS) — heat insulation and lining of the face.
- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 33%.
Erection of Arch western part steelwork:
Erected in total – 30,552.99 t