- Development of work execution plans (flow sheets) for installation of equipment and systems.
- Installation of Technological Process Monitoring and Control System (TP MCS) cabinets.
- Mounting of cable routing structures for PPS, AMS and RMS
- Cable routing.
- Installation of main process equipment:
* Works on modification of shielding door SFP-SD-08 in prem. 403/IS 102 C6.
* Assembling of racks for 200-l drums.
* Pit covers No.1 and No.3 SFP-XP-210/211, prem. 501 were installed
- Installation of extra embedded items for the docking device.
- Preparatory works for installation of the docking device TK-8 cup.
- Electrical installation works on gateways of small-sized elements, holder slide.
- Installation of control cabinets for ventilation system fire protection valves.
- Mounting of ducts, cable laying, connection of control cabinets for ventilation system fire protection valves.
- Installation of FGD pipelines.
- Fire protection of ventilation system air ducts.
- Filling of shielding door SFP-SD-02 with lead pellets, prem. 109А/111А.
- Works on RMS gas-aerosol monitoring systems.
- Soldering of optic cable from ZVSB to Control Panel 1 at the checkpoint.
- Completing of as-built documents and deliverables for handing-over the relevant stages in accordance with the Contract.
- Development of testing programs for process units and systems and training programs for the Client’s personnel.
The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 200 persons were engaged in the works. 5 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.
* Technological building (TB) — works related to polishing, pre-coating, coating and painting of walls and ceilings inside the building. Installation of supports and fire-fighting water supply pipelines, doors;
* Electrical Equipment Building (EEB) — works related to installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems and steel structures.
* Installation of anchors of the west end wall;
* Pre-assembly and preparation of flashing anchors for installation;
* Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment. Installation of ventilation equipment piping in NVC and SVC.
* Installation of fire fighting and drinking water pipelines;
* Heat insulation of pipelines of external utilities rack;
* Construction of roads in Local zone — 36%.
* Weight of Arch erected steelwork — 30,552 t;
* Works on moving the Arch into its design position are completed;
* Dismantling of the Arch sliding tracks in the Erection area.
- Installation of Technological Process Monitoring and Control System cabinets in the SFPF building — installation of AWS.
- Mounting of cable routing structures for PPS, AMS and RMS within the SFPF building premises.
- Installation of lighting system within prem. -101, -103, -104 (level -3,000) at the SFPF
- Installation of main process equipment:
* Works on modification of a protection hatch (ceiling gate) of prem. IS 102 C6.
* Assembling of racks for 200-l drums.
* Preparatory works for installation of transport container trolleys (prem. 114) SFP-TD-05; SFP-TD-06.
* Installation of pit covers No. 1 and No. 3 SFP-XP-210/211, prem. 501.
- Drilling of holes at flooring 501/107 (installation of additional embedded items for a docking device).
- Electrical installation works on gateway of small-sized elements, holder slide.
- Installation of control cabinets for ventilation system fire protection valves.
- Mounting of ducts, cable laying, connection of control cabinets for ventilation system fire protection valves.
- Installation of FGD pipelines.
- Fire protection of ventilation system air ducts.
- Soldering of optic cable from ZVSB to Control Panel 1 at the checkpoint.
- Completing of as-built documents and deliverables for handing-over the relevant stages in accordance with the Contract.
- Development of testing programs for process units and systems and training programs for the Client’s personnel.
The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 193 persons were engaged in the works. 5 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.