Erection of Arch steelwork

• Installation of the sealing anchor beams on the roofs of Block V;
• Drilling of holes for installation of sealing anchors at elev. +75.583.

Technological building and auxiliary facilities

• Installation of the following main systems:
- Power supply system;
- Ventilation, gas purification and conditioning;
- Fire safety system;
- Water supply and sewerage system;
- Communication and industrial TV system;
- Physical protection and access control system;
- Integrated management and control system;
- System of internal and transport connection;
- Radiation monitoring system;
• Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

Fire extinguishing pump station building with tanks

• Electrical fitting works are in progress. Installation of a system of exhaust gases from diesel-driven pumps;
• Final painting of walls and ceilings.

Works on arranging the NSC internal and external space

• Pipelines installation;
• Weather station establishment.

Other activity

• Dismantling of the Turbine Hall light roof.

Select another date

Erection of Arch steelwork

• Installation of the sealing anchor beams on the roofs of Block V;
• Installation of the membrane on the roof of Block V.

Technological building and auxiliary facilities

• Installation of the following main systems:
- Power supply system;
- Ventilation, gas purification and conditioning;
- Fire safety system;
- Water supply and sewerage system;
- Communication and industrial TV system;
- Physical protection and access control system;
- Integrated management and control system;
- System of internal and transport connection;
- Radiation monitoring system;
• Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

Fire extinguishing pump station building with tanks

• Electrical fitting works are in progress. Installation of a system of exhaust gases from diesel-driven pumps.

Works on arranging the NSC internal and external space

• Pipelines installation;
• Weather station establishment.

Other activity

• Dismantling of the Turbine Hall light roof.

Select another date

Within the project the following activity was performed at the construction site:

- works on insulation of pipelines and forced gas drying system heaters;
- sealing of IAEA equipment, installation of locks;
- cable laying, installation of sockets;
- drilling of holes and screw cutting in the concrete storage modules doors;
- electrical works at the SWP-CR-04 crane;
- installation of electronic key system;
- reconfiguration of the Ventilation System fire protection valves;
- adjustment of gaps and welding of the sleeves of technological pipelines penetrations;
- fire retardant sealing of technological pipelines penetrations of process pipelines;
- scheduled works for the construction site improvement;
- compilation of the executive and hand-over documentation;
- development of technological units and systems testing programs;
- development of Customer's personnel training programs;
- pre-commissioning activity at the basic technological equipment and auxiliary systems;
- individual testing of the System for technological process monitoring and controlling at the - systems for fuel canisters, double-wall shielded canisters handling and solid radioactive waste management;
- software finalization and adjustment of the temperature control system for concrete storage modules;
- loading of double-wall shielded canister in the System of canisters manipulation and transportation and trial delivery into the concrete storage module;
- elimination of comments based on the results of individual tests of the device for spent fuel assemblies cutting SFP-CS-205;
- individual testing Systems for the canister CHT-TD-02 handling and transporting;
- elimination of comments based on the results of the trolley TD-05/06 individual testing;
- individual testing of the system of the fuel canister double lid;
- individual tests of protective lids SHIELDING PLUGS 305 SFP-XP-210/211;
- pilot operation of the Physical Protection System.

The Project General Contractor is Holtec. Works on the site are performed by the involved by Holtec subcontractors: CPI, UTEM, UTB, ZEM, EPI, BEM, “Kranservice”, “Conditioner”. In total 141 people were involved, as well as 1 units of transporting equipment.

December 19, 2017
December 19, 2017
December 19, 2017
December 19, 2017
December 19, 2017
December 19, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Installation of the sealing anker beams on the roofs of Block V;
* Installation of the membrane on the roof of Block V.

- Technological building and auxiliary facilities:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system
* Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

- Fire extinguishing pump station building with tanks:

* Electrical fitting works are in progress. Installation of a system of exhaust gases from diesel-driven pumps;

- Works on arranging the NSC internal and external space:

* Pipelines installation;
* Weather station establishment.

Other activity:

* Dismantling of the Turbine Hall light roof.

 

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Installation of the sealing anker beams on the roofs of Block V.

- Technological building and auxiliary facilities:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system
* Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

- Works on arranging the NSC internal and external space:

* Pipelines installation;
* Site improvement activity;
* Weather station establishment.

Other activity:

* Dismantling of the Turbine Hall light roof.