Spent Fuel Processing Facility (SFPF):

- Unloading of the equipment and materials, equipment transfer into the installation area.
- Installation of cable products of АC and RMS in SFPF building premises.
- Modification of the bridge crane SFP-CR-07 and gantry crane SFP-CR-08 in the room p. 305 — electrical works.
- Modification of the bridge crane SFP-CR-11 in the room 501/603 — replacement of mechanical and electrical components.
- Modification of the bridge crane SFP-CR-01 in prem. 119 — replacement of the electrical components.
- Electrical and installation work on modification of the protective hatch in the prem. IS102C6 of SFPF building.
- Installation of main process equipment:
     * Installation of the docking device TK-8.
     * Installation of the SFP-TT-210 table in prem. 501 (the welding of the table lining is completed), geodetic acceptance of the installed elements.
     * Installation of power and control cables of BNG equipment.
     * Rerouting and installation of air ducts and fire retardant valves for rev. 12 ventilation in SFPF building.
     * Assembling of stainless ducts in the joints and air ducts installation in prem. 606, 606A.
     * Installation of cable routes in premise 405 for air-supply ventilation in automation system.
- Works in gas-aerosol control systems in RMS.
- Work on installation openings closure in the prem. 705 — roof arrangement.

The following activities were also performed at the facility:

- Completion of the staircase C3-1 installation.
- Fiber optic cable soldering, connection of PPS system sensors.
- Installation of PPS lightning protectors.
- Compilation of executive and hand-over documentation for the corresponding stages delivery according to the Contract.
- Development of testing programs for technological units and systems.
- Theoretical training for the Employer’s personnel.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 305 persons were engaged in the works. 4 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

April 03, 2017
April 03, 2017
April 03, 2017
April 03, 2017
April 03, 2017
April 03, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

 * Technological building (TB) — work on arrangement of the facade of the building eastern part. Installation of cable ducts, cabling. Preparation for crane beam installation for the 20 ton crane. Reassembly of 20 ton crane. Installation of fire alarm system. Works inside the building on polishing, coating, putty, painting of floors, walls and ceilings. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of fire-alarm system. Installation of cable trays, cable laying;
* Access Gateway for Fire brigades – installation of internal networks pipelines, installation of equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors.

Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Construction of roads in Local zone — 45%.

- Erection of Arch steelwork:

* Installation of the following main systems:
  • Power supply system;
  • Ventilation, gas purification and conditioning;
  • Fire safety system;
  • Water supply and sewerage system;
  • Communication and industrial TV system;
  • Physical protection and access control system;
  • Integrated management and control system;
  • System of internal and transport connection;
  • Radiation monitoring system;
Contractor also performs installation of the MCS trolleys moving system in the northern garage. Work has started to install the small lifting devices in the technological building;

Completion of the works on exterior and interior facing;
* Concreting of the Arch's permanent articulated supports is performed. The work on load transferring to the permanent articulated supports is completed. Contractor performs dismantling of hydraulic jacks;
* Preparation for sealing anchors installation.

March 29, 2017
March 29, 2017
March 29, 2017
March 29, 2017
March 29, 2017
March 29, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

 * Technological building (TB) — work on arrangement of the facade of the building eastern part. Installation of cable ducts, cabling. Preparation for crane beam installation for the 20 ton crane. Reassembly of 20 ton crane. Installation of fire alarm system. Works inside the building on polishing, coating, putty, painting of floors, walls and ceilings. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of fire-alarm system. Installation of cable trays, cable laying;
* Access Gateway for Fire brigades – installation of internal networks pipelines, installation of equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors.

Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Construction of roads in Local zone — 42%.

- Erection of Arch steelwork:

* Installation of the following main systems:
  • Power supply system;
  • Ventilation, gas purification and conditioning;
  • Fire safety system;
  • Water supply and sewerage system;
  • Communication and industrial TV system;
  • Physical protection and access control system;
  • Integrated management and control system;
  • System of internal and transport connection;
  • Radiation monitoring system;
Contractor also performs installation of the system of MCS trolleys movement in the northern garage;

Completion of the works on exterior and interior facing;
* Installation of sealing disk;
* Concreting of Arch permanent pivot mounting;
* Preparation for sealing anchors installation.

Select another date

Spent Fuel Processing Facility (SFPF):

- Unloading of the equipment and materials, equipment transfer into the installation area.
- Installation of cable lines of Physical Protection System, Automated monitoring and Radiation monitoring System.
- Cable routing.
- Bridge cranes SFP-CR-07, SFP-CR-1, SFP-CR-01 and gantry crane SFP-CR-08 modification — replacement of mechanical and electrical components.
- Installation of main process equipment:
     * Installation of crane beams in prem. IS102C9; Crane supports  in prem. 403.
     * Work has started to modify the protective hatch in the room IS102C6.
     * Installation of power and control cables of BNG equipment.
     * Re-routing and installation of air ducts and fire retardant valves for ventilation.
     * Assembly of stainless air ducts and installation of air ducts in a hot cell — in prem. 501 and in prem. 606, 606A.
     * Installation of cable routes in rooms 405, 606/606А, 704 for air-supply ventilation equipment through the automation system.
- Gas-aerosol control systems for RMS system.
- Work on installation openings closing.
- Work on  new laboratory premise 211 arrangemen.
- Installation of duplicating manipulators SFP-TM-221/222 in prem. 305 / 303A and SFP-TM-227/228 in prem. 501/506 was completed, electrical works are started.
- Installation of equipment and cable lines of the fire alarm and evacuation control system has been completed - except for the installation openings, supporting ring (segments) of TK-8 docking device cup, bottom perforators in prem. 305, seismic locks on security doors, rack bars of existing transport containers trolleys SFP-TD-05 / SFP-TD-06 (room 114), installation of alarm lighting system BNG.

The following activities were also performed at the facility:

- Connection of video cameras, soldering of fiber optic cable, assembly of Physical Protection System elements.
- Repaired hydraulic cylinders, hydraulic motors and hydraulic pumps are installed, adjustment works are underway
- Completing of the executive and handover documentation to delivery the relevant stages under the Contract.
- Development of tests programs for technological components and systems, customer's personnel training programs.
- Pre-commissioning on a sliding holder, cutting device and double lid system.
- Individual testing of the equipment - primary tests of SFP-CR-06 SFP-CR-04, SWP-CR-01 cranes is completed.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 288 persons were engaged in the works. 3 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

March 10, 2017
March 10, 2017
March 10, 2017
March 10, 2017
March 10, 2017
March 10, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

 * Technological building (TB) — work on arrangement of the facade of the building eastern part. Installation of cable ducts, cabling. Preparation for crane beam installation for the 20 ton crane. Reassembly of 20 ton crane. Installation of fire alarm system. Works inside the building on polishing, coating, putty, painting of floors, walls and ceilings. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of fire-alarm system. Installation of cable trays, cable laying;
* Access Gateway for Fire brigades – installation of internal networks pipelines, systems, steel structures;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors.

Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Arrangement of the thermal insulation of pipelines external engineering networks overpass;
* Construction of roads in Local zone — 41%.

- Erection of Arch steelwork:

* Installation of the following main systems:
  • Power supply system;
  • Ventilation, gas purification and conditioning;
  • Fire safety system;
  • Water supply and sewerage system;
  • Communication and industrial TV system;
  • Physical protection and access control system;
  • Integrated management and control system;
  • System of internal and transport connection;
  • Radiation monitoring system;
Contractor also performs installation of the system of MCS trolleys movement in the northern garage;

Arch facing is tested for leakage;
Completion of the works on exterior and interior facing;
* Concreting of Arch permanent pivot mounting;
* Pre-assembly, assembly and preparation for sealing anchors installation.