Spent Fuel Processing Facility (SFPF):

- Development of work performance projects (technological sheets) for fire retention sealing of the penetrations.
- Unloading of the equipment and materials, equipment delivery into the installation area.
- Modification of the bridge crane SFP-CR-11 in the prem. 501 — installation of the electrical part is underway.
- Modification of the bridge crane SFP-CR-07 in the prem. 305 — installation of the electrical part completed.
- Modification of the gantry crane SFP-CR-08 in the prem. 305 — installation of the electrical part is underway.
- Electrical installation work on crane SWP-CR-206 in the prem. 403 and cables disconnection.
- Installation of electrical part — bridge crane MIS-CR-221 (prem 603).
- Installation of embedded parts for manual lifting tackles in SFPF building.
- Installation of main process equipment:
   * Installation of refrigeration supply system in the caisson 107c (connetion to CAV-RS-13, CAV-RS-14, CAV-RS-01).
   * Installation of pipelines of the technological blowdowns system in SFPF.
   * Installation and wiring work on SFPF equipment pinout.
   * Installation of a stationary high-pressure apparatus Kärcher is completed.
   * Modification of the mounting seat for the protective lid of the canister manipulation and transportation (CMTS) system — manufacturing of the components for modification, dismantling of the existing metal structures.
   * Installation of power and control cables of BNG equipment.
- Laying and pinout of BNG lighting cables in the SFPF premises.
- Works on the installation openings closing in prem. 603 — roof arrangement.

The following activities were also performed at the facility:

- Finishing of the SFPF building premises.
- Installation of fore-roof metal structures for pressure vessels.
- Compilation of executive and hand-over documentation.
- Development of testing programs for technological units and systems.
- Development of training programs for the Customer's personnel.
- Theoretical training for the personnel.
- Pre-commissioning work on the cutting facility, RMS system, chemically demineralized water system and ventilation system.
- Completion of individual tests of the lock for small-sized elements (LSE) SWP-TD-221.
- Individual testing of the hot cell filters CAV-FR-213 and lids of wells No. 1 & 3 (SFP-CG-212, SFP-CG-213).

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 268 persons were engaged in the works. 4 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

June 08, 2017
June 08, 2017
June 08, 2017
June 08, 2017
June 08, 2017
June 08, 2017

Select another date

Spent Fuel Processing Facility (SFPF):

- Unloading of the equipment and materials, equipment transfer into the installation area.
- The electrical installation work at the crane MIS-CR-240 in prem. IS102c9 are completed.
- Works on the bridge crane SFP-CR-01 modification in prem. 119 are underway in terms of the electrical part.
- Works on the bridge crane SFP-CR-07 modification in prem. 305 are underway in terms of the electrical part.
- Works on the gantry crane SFP-CR-08 modification in prem. 305 are underway in terms of the electrical part.
- Finishing (including the floor painting) in prem. 119 of the SFPF building is completed.
- Installation of main process equipment:
     * Installation of bottom frame of the caisson 107c.
     * Installation of FFS pipelines in prem. 505 A and 505 B of the SFPF building without the valve mounting has been completed (delivery is expected).
     * Re-tracing the fire-fighting pipeline inside the SFPF building.
     * Installation of power and control cables of BNG equipment.
- Works on the installation openings closing in prem. 603 — рarapet arrangement.

The following activities were also performed at the facility:

- Installation of the external fire escape stair P2 and the installation of the SG-5 ladders has been completed .
- Finishing of the SFPF building premises.
- Arrangement of the arms room in the checkpoint.
- Installation of fore-roof metal structures for pressure vessels.
- Extension of seismic restrains on CSM modules.
- Compilation of executive and hand-over documentation for the corresponding stages delivery according to the Contract.
- Development of testing programs for technological units and systems.
- Development of training programs for the Customer's personnel.
- Conducting of theoretical training for the Customer's personnel.
- Pre-commissioning work at the cutting facility, RMS system, chemically demineralized water system and ventilation system.
- Conducting of individual tests of the lock for small-sized elements (LSE).

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 266 persons were engaged in the works. 3 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

May 24, 2017
May 24, 2017
May 24, 2017
May 24, 2017
May 24, 2017
May 24, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Technological building and auxiliary facilities:

* Technological building (TB) — work associated with arrangement of the facade of the building eastern part. Installation of cable ducts, cabling is underway. Crane beams for the 20 ton crane are being installed. Reassembly of 20 ton crane. The crane has been lifted to the design reference mark. Installation of Fire Alarm System. Installation of air ducts of the ventilation system. Works inside the building on polishing, priming, filling up with putty, pouring, painting of floors, walls and ceilings are underway. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of Fire Alarm System. Installation of cable ducts, cable laying;
* Access Gateway for Fire brigades — installation of internal networks pipelines, installation of the equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors;
* Storm Water Dispersal Plant — activities on water drawdown and foundation construction, dewatering of the site sump. The tanks of dispersal plant are being installed.

- Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Arrangement of Arch end walls;
* Arrangement of the area for southern gallery of articulated supports near the turbine hall;

* Construction of roads in Local zone — 65%.

- Erection of Arch steelwork:

* Installation of the following main systems:
• Power supply system;
Ventilation, gas purification and conditioning;
Fire safety system;
Water supply and sewerage system;
Communication and industrial TV system;
Physical protection and access control system;
Integrated management and control system;
System of internal and transport connection;
Radiation monitoring system;
* The Contractor also completed installation of the MCS trolleys moving system in the northern garage. The MCS control cabinets are being installed in the central control room. Connection of control boards to the central control room;

* Work is underway to install small lifting devices in the technological building;
* Completion of external and internal facing;
* Preparation for installation and installation of sealing anchors on the roof of TB and Access Gateway for Fire Brigades;
* Installation of the sealing membrane is underway.

May 25, 2017
May 25, 2017
May 25, 2017
May 25, 2017
May 25, 2017
May 25, 2017
May 25, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Technological building and auxiliary facilities:

* Technological building (TB) — work associated with arrangement of the facade of the building eastern part, installation of cable ducts, cabling are underway. Crane beams for the 20 ton crane are being installed. Reassembly of 20 ton crane. The crane has been lifted to the design reference mark. Installation of Fire Alarm System. Works inside the building on polishing, priming, filling up with putty, pouring, painting of floors, walls and ceilings are underway. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of Fire Alarm System. Installation of cable ducts, cable laying;
* Access Gateway for Fire brigades — installation of internal networks pipelines, installation of the equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors;
* Storm Water Dispersal Plant — activities on water drawdown and foundation construction, dewatering of the site sump. The tanks of dispersal plant are being installed.

- Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Arrangement of Arch end walls;
* Arrangement of the temporary storage area within the main volume of building to the east of the Process Building;
* Arrangement of the area for southern gallery of articulated supports near the turbine hall;

* Construction of roads in Local zone — 64%.

- Erection of Arch steelwork:

* Installation of the following main systems:
• Power supply system;
Ventilation, gas purification and conditioning;
Fire safety system;
Water supply and sewerage system;
Communication and industrial TV system;
Physical protection and access control system;
Integrated management and control system;
System of internal and transport connection;
Radiation monitoring system;
* The Contractor is arranging the system of MCS trolleys moving to the northern garage. The MCS control cabinets are being installed in the central control room;

* Work is underway to install the small LLD in PB;
* Activities on exterior and interior facing are drawing towards completion;
* Preparation for installation and installation of sealing anchors on the roof of PB and Access Gateway for Fire Brigades;
* Installation of the sealing membrane is underway.

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Technological building and auxiliary facilities:

* Technological building (TB) — work associated with arrangement of the facade of the building eastern part, installation of cable ducts, cabling are underway.  Crane beams for the 20 ton crane are being installed. Reassembly of 20 ton crane. The embedded items for arrangement of crane beams for the 20 ton crane are being installed. The crane has been lifted to the design reference mark. Installation of Fire Alarm System. Works inside the building on polishing, priming, filling up with putty, pouring, painting of floors, walls and ceilings are underway. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of Fire Alarm System. Installation of cable ducts, cable laying;
* Access Gateway for Fire brigades — installation of internal networks pipelines, installation of the equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors.

- Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Arrangement of the temporary storage area within the main volume of building to the east of the Process Building;
* Arrangement of the area for southern gallery of articulated supports near the turbine hall;

* Construction of roads in Local zone — 61%.

- Erection of Arch steelwork:

* Installation of the following main systems:
• Power supply system;
Ventilation, gas purification and conditioning;
Fire safety system;
Water supply and sewerage system;
Communication and industrial TV system;
Physical protection and access control system;
Integrated management and control system;
System of internal and transport connection;
Radiation monitoring system;
* The system of MCS trolleys moving to the northern garage is being arranged. Work is underway to install the small load-lifting devices in the process building;

* Activities on exterior and interior facing are drawing towards completion;
* Preparation for installation and installation of sealing anchors on the roof of process building and Access Gateway for Fire Brigades;
* Installation of the sealing membrane is underway.