Within the NSC Project at the construction site the following works are being performed:
- Second lifting of the Arch is performed
- Arrangement of inclined piles in the serviced area (northern slip foundations)
- Reinforcement of the serviced area (northern slip)
- Activities on arranging an engineering building

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 3,788.6 tons
3,788.6 tons (100%) performed

Mounting of the roof covering of the Arch:
Surface area of roof cladding before 2nd lifting - 13,952.2 m2, 96.37% performed.
Surface area of internal cladding before 2nd lifting – 12,468.15 m2, 89.26% performed

Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 1,058 m3 (99.81%);
- Design pile amount – 208 piles, placed till design mark – 122 piles (58.65%)

Select the another date

Within the NSC Project at the construction site the following works are being performed:

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 3,788.6 tons
3,788.6 tons (100%) performed

Mounting of the roof covering of the Arch:
Surface area of roof cladding before 2nd lifting - 13,952.2 m2, 94.3% performed.
Surface area of internal cladding before 2nd lifting – 12468.15 m2, 81.1% performed

Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 1,058 m3 (99.81%);
- Design pile amount – 208 piles, placed till design mark – 107 piles (51.44%)

Select the another date

Within the NSC Project at the construction site the following works are being performed:

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons
3,720.63 tons (90.81%) performed

Installation of the Arch roof’s outer cladding:
Surface area of roof cladding before 2nd lifting - 13,952.2 м2.
Overall progress in the Arch outer cladding installation before 2nd lifting – 79%

Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 1,058 m3 (99.81%);
- Design pile amount – 208 piles, placed till design mark – 74 piles (35.6%)

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Assembling of basic and supporting structures of the Arch;
- Assembling of guiding slide supports for Lifting No.2;
- Assembling of air ducts of the Arch;
- Assembling of crane beams of the main crane system;
- Assembling of external and internal casing of the Arch;
- Arrangement of base concrete for pile field in the serviced area (northern slip foundations);
- Arrangement of inclined piles in the serviced area (northern slip foundations);
- Excavations on arranging an engineering building.

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons
3,593.38 tons (87,7%) performed

Installation of the Arch roof’s outer cladding:
Surface area of roof cladding before 2nd lifting - 13,952.2 м2.
Overall progress in the Arch outer cladding installation before 2nd lifting – 53.3%

Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 773 m3 (73%);
- Design pile amount – 208 piles, placed till design mark – 54 piles (26%)