Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Installation of runway beam suspension supports for main crane system;
- Preparation of containers for jacking the West Part of the Arch;
- Preparation of equipment for movement of the Eastern part of the Arch into the stand-by area;
- Preliminary assembling of casing panels;
- Installation of casing girders;
- Assembling of external and internal casing;
- Supply and installation of stainless steel air ducts;
- Arrangement of the service zone foundations (foundation frame of Southern trench);
- Isntallation of CFA piles of service area foundation (Southern trench);
- Arrangement of engineering building and auxiliary facilities;
- movement of the Eastern part of the Arch in the waiting area (the work is done). 

Assembling of the Arch West part (before 1st jecking):
Total weight of metal structures – 4,513 tons.
Metal structures assembled in total – 3,610.37 tons (80%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,743.109 tons
Metal structures assembled in total – 12,749.84 tons (92.77%).

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 5,674.2 m3 (48.1%); 
Design amount of rebars - 2,447.009 tons, rebar fabrication – 1,411.943 tons (57.70%).

Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 126 piles (58.33%)

31 березня 2014 року
02 квітня 2014 року

 

 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Installation of runway beam suspension supports for main crane system;
- Preparation of containers for jacking the West Part of the Arch;
- Preparation of equipment for movement of the Eastern part of the Arch into the stand-by area;
- Preliminary assembling of casing panels;
- Installation of casing girders;
- Assembling of external and internal casing;
- Arrangement of the service zone foundations (foundation frame of Southern trench);
- Isntallation of CFA piles of service area foundation (Southern trench);
- Arrangement of engineering building and auxiliary facilities. 

Assembling of the Arch West part (before 1st jecking):
Total weight of metal structures – 4,513 tons.
Metal structures assembled in total – 3,495.55 tons (77.46%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,743.109 tons
Metal structures assembled in total – 12,749.84 tons (92.77%).

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 5,674.0 m3 (48.0%); 
Design amount of rebars - 2,447.009 tons, rebar fabrication – 1,376.438 tons (56.25%).

Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 117 piles (54.16%)

 

March 27, 2014
March 27, 2014
March 27, 2014
March 27, 2014
March 27, 2014
March 27, 2014

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Installation of runway beam suspension supports for main crane system;
- Preparation of containers for jacking the West Part of the Arch;
- Preparation of equipment for movement of the Eastern part of the Arch into the stand-by area;
- Preliminary assembling of casing panels;
- Installation of casing girders;
- Assembling of external and internal casing;
- Rail installation on removable modules for sliding (basis of Arch installation area);
- Arrangement of the service zone foundations (foundation frame of Northern trench);
- Isntallation of CFA piles of service area foundation (Southern trench);
- Arrangement of engineering building and auxiliary facilities. 

Assembling of the Arch West part:
Total weight of metal structures – 3,755 tons.
Metal structures assembled in total – 3,284.96 tons (87.48%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,743.109 tons
Metal structures assembled in total – 12,749.84 tons (92.77%).

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 5,638.0 m3 (47.80%); 
Design amount of rebars - 2,447.009 tons, rebar fabrication – 1,318.370 tons (53.87%).

Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 110 piles (50.93%)

 

March 20, 2014
March 20, 2014
March 20, 2014
March 20, 2014
March 20, 2014
March 20, 2014

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Assembling of bearing and hoisting towers;
- Preparation of containers for jacking the West Part of the Arch;
- Preparation of equipment for movement of the Eastern part of the Arch into the stand-by area;
- Preliminary assembling of casing panels;
- Installation of casing girders;
- Assembling of external and internal casing;
- installation of removable blocks (foundation of Arch’s erection area);
- Arrangement of the service zone foundations (foundation frame of Northern trench);
- Isntallation of CFA piles of service area foundation (Southern trench);
- Arrangement of engineering building and auxiliary facilities. 

Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total – 2,905.33 tons (87.43%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,392.5 tons
Metal structures assembled in total – 12,732.84 tons (94.0%).

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 5,545.0 m3 (47.0%); 
Design amount of rebars - 2,447.009 tons,
rebar fabrication – 1,283.333 tons (52.44%).

Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 98 piles (45.37%)

  

March 13, 2014
March 13, 2014
March 13, 2014
March 13, 2014
March 13, 2014
March 13, 2014
 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Assembling of bearing and hoisting towers;
- Preparation of containers for jacking the West Part of the Arch;
- Preparation of equipment for movement of the Eastern part of the Arch into the stand-by area;
- Preliminary assembling of casing panels;
- Installation of casing girders;
- Assembling of external and internal casing;
- Arrangement of the service zone foundations (foundation frame of Northern trench);
- Isntallation of CFA piles of service area foundation (Southern trench);
- Arrangement of engineering building and auxiliary facilities. 

Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total – 2,667.22 tons (80.27%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,392.5 tons
Metal structures assembled in total – 12,732.84 tons (94.0%).

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 5,545.0 m3 (47.0%); 
Design amount of rebars - 2,447.009 tons, 
rebar fabrication – 1,283.333 tons (52.44%).

Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 92 piles (42.59%)

 

March 06, 2014
March 06, 2014
March 06, 2014
March 06, 2014
March 06, 2014
March 06, 2014