Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of external and internal casing;
- Installation of main beams of the casing;
- Revision of containers for the Arch jacking;
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;
- Works on technological building and auxiliary facilities arrangement are underway:
     * Engineering building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concrete curing;
      * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing.
- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch till 3rd lifting:
Metal structures assembled in total – 10,561.8 tons.

Concreting of the Technological building foundation slab:
Design volume of concrete is 6,606 m3, 6,170 m3 is laid (93%)
Designed quantity of reinforcement is 1,375 tons, 1,279 tons is produced (93%)

 

September 25, 2014
September 25, 2014
September 25, 2014
September 25, 2014
September 25, 2014
September 25, 2014
 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of external and internal casing;
- Installation of main beams of the casing;
Jacking towers assembly / disassembly;
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;
- Works on technological building and auxiliary facilities arrangement are underway:
     * Engineering building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concrete curing;
     * Control room in the process building - preparatory work prior the foundation slab reinforcement; 
     * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing.
- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch till 3rd lifting:
Metal structures assembled in total – 10,463.82 tons.

Concreting of the Technological building foundation slab:
Design volume of concrete is 6,606 m3, 6,170 m3 is laid (93%)
Designed quantity of reinforcement is 1,375 tons, 1,279 tons is produced (93%)

 

September 18, 2014
September 18, 2014
September 18, 2014
September 18, 2014
September 18, 2014
September 18, 2014
 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of external and internal casing;
- Installation of main beams of the casing;
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;
- Preparation of paths for moving jacking towers and movement of hoisting towers for 3rd lifting of Western part of the Arch;
- Works on technological building and auxiliary facilities arrangement are underway.
     * Engineering building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concrete curing;
     * Electrical device building – reinforcing, installation of formwork for wall arrangement.
- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch till 3rd lifting:
Metal structures assembled in total – 10,328.44 tons.

Concreting of the Technological building foundation slab:
Design volume of concrete is 6,606 m3, 6,170 m3 is laid (93%)
Designed quantity of reinforcement is 1,375 tons, 1,279 tons is produced (93%)

 

September 11, 2014
September 11, 2014
September 11, 2014
September 11, 2014
September 11, 2014
September 11, 2014
 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of external and internal casing;
- Installation of main beams of the casing;
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;
- Preparation of paths for moving jacking towers and movement of hoisting towers for 3rd lifting of Western part of the Arch;
- Dismantling of tension and blocking system, coiling of steel wire rope, lowering of jacking beams and their dismantling;
- Works on technological building and auxiliary facilities arrangement are underway.
     * Engineering building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concrete curing;
     * Electrical device building – reinforcing, installation of formwork for wall arrangement.
- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch till 3rd lifting:
Metal structures assembled in total – 10,276.01 tons.

Concreting of the Technological building foundation slab:
Design volume of concrete is 6,194 m3, 3,185 m3 is laid (51.4%)
Designed quantity of reinforcement is 1,375 tons, 1,375 tons is produced (100.0%)

 

September 04, 2014
September 04, 2014
September 04, 2014
September 04, 2014
September 04, 2014
September 04, 2014
 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of external casing at the East Arch southern section;
- Installation of main beams of the casing (Western Arch);
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;
- Preparation of jacking towers sliding ways (movement) for 3rd lifting of the Western Arch;
- Dismantling of tension and blocking system, coiling of steel wire rope;
- Installation of structures and casing of swing panel ОП-1 of the Eastern part of Arch;
- Works on technological building and auxiliary facilities arrangement are underway.
* Engineering building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concrete curing;
* Electrical device building – reinforcing, installation of formwork for wall arrangement.

On August 26, 2014, after second jacking, the Western part of Arch is lowered and fixed on holding devices transferring 100% load to the foundations.

Assembly of metal structures of Western section of the Arch till second lifting completion:
Metal structures assembled in total – 10,261.601 tons.

Concreting of the Technological building foundation slab:
Design volume of concrete is 6,194 m3, 3,185 m3 is laid (51.4%)
Designed quantity of reinforcement is 1,375 tons, 1,347 tons is produced (98.0%)

Arrangement of peripheral walls of Technological building:
Designed concreting (walls and ceilings) - 10146 m3, 96 m3 was laid (1.0%)
Metal structures (walls and ceilings) - 3,228.54 tons, 54.49 tons was mounted (1.69%)

 

August 28, 2014
August 28, 2014
August 28, 2014
August 28, 2014
August 28, 2014
August 28, 2014