Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and assembly of main structures of the Western part of Arch;
- Installation of metal structures of Arch Western part filling;
- Preparation and completion of purlines for clading before installation;
- Dismantle of jacking beams;

- Works on technological building and auxiliary facilities arrangement are underway:
     * Techological building - dismantle of formwork for wall arrangement, snow removal;
     * Electrical device building - dismantle of slab formwork, snow removal;

- Arrangement of internal and external space of NSC (northern side):
     * End walls of the Arch;
     * Storm water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total –  12,933.57 tons

January 15, 2015
January 15, 2015
January 15, 2015
January 15, 2015
January 15, 2015
January 15, 2015
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of cladding purlines;
- Installation of internal and external cladding;
- Dismantle of lifting towers;
- Preparation for transportation and removal of Mammoet equipment from the site;
- Delivery and installation of air ducts, preparation for installation;

- Works on technological building and auxiliary facilities arrangement are underway:
     * Techological building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concreting, concrete curing;
      * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing;
      * firefighting unit access airlocks - concreting of foundation slab completed, concrete curing.

- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total –  12,933.57 tons

Concreting of the Technological building and electrical devices building foundation slab:
Design volume of concrete is 6,542 m3, laid 6,448м3 (98%) 
Designedy ammount of reinforcement is 1,375 tons, prodeced 1,333 tons (98%)

 

December 18, 2014
December 18, 2014
December 18, 2014
December 18, 2014
December 18, 2014
December 18, 2014
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of cladding purlines;
- Installation of internal and external cladding;
- Dismantle of lifting towers;
- Preparation for transportation and removal of Mammoet equipment from the site;
- Delivery and installation of air ducts, preparation for installation;

- Works on technological building and auxiliary facilities arrangement are underway:
     * Techological building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concreting, concrete curing;
      * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing;
      * firefighting unit access airlocks - concreting of foundation slab completed, concrete curing.

- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total –  12915.57 tons

Concreting of the Technological building and electrical devices building foundation slab:
Design volume of concrete is 6542 m3, laid 6448м3 (98%) 
Designedy ammount of reinforcement is 1375 tons, prodeced 1333 tons (98,0%)

 

December 11, 2014
December 11, 2014
December 11, 2014
December 11, 2014
December 11, 2014
December 11, 2014
  

 

Select the another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery to the site and assembly of main structures of the Western part of Arch;
- Installation of main metal structures of the Western part of Arch;
- Installation of cladding purlines;
- Installation of internal and external cladding;
- Dismantle of lifting towers;
- Delivery and installation of air ducts, preparation for installation and installation of air ducts and supports in the annular space of the Western and Eastern parts of Arch;

- Works on technological building and auxiliary facilities arrangement are underway:
     * Techological building – assembly of foundation slab and wall reinforcement, installation of formwork for wall arrangement, concreting, concrete curing;
      * electrical devices building - walls reinforcement installation, assembling of casing for the walls arrangement, concreting, concrete curing;
      * firefighting unit access airlocks - concreting of foundation slab completed, concrete curing.

- Arrangement of internal and external space of NSC:
     * End walls of the Arch;
     * Walls of hinged bearing gallery;
     * Storm water catchment basins;
     * Fire water catchment basins;
     * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:

Metal structures assembled in total –  12903,471 tons

Concreting of the Technological building and electrical devices building foundation slab:
Design volume of concrete is 6542 m3, laid 6448м3 (98%) 
Designedy ammount of reinforcement is 1375 tons, prodeced 1333 tons (98,0%)

 

December 04, 2014
December 04, 2014
December 04, 2014
December 04, 2014
December 04, 2014
December 04, 2014

The New Safe Confinement. Construction Chronicle

November 24,  2012, the first lifting of the Arch Eastern part

June 12-14,  2013, the second lifting of the Arch Eastern part

March 31 - April 02, 2014, the skidding of the Arch Eastern part to the waiting area

April 26-27, 2014, the first lifting of the Arch Western part

August 02-03, 2014, the second lifting of the Arch Western part

October 23-24, 2014, the third lifting of the Arch Western part

 

November 26, 2014, the back skidding of the Arch Eastern part

 {flv}news27-11-14_nsc{/flv}

November 14-27, 2016. The Final Movement. Chernobyl NSC Sarcophagus Skidding