Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and completing main metal structures of the Arch;
- Assembly of metal structures of tilting panels TP-5-1, TP-5-2, TP-6;
- Assembly of bridging elements of main metal structures of western part of the Arch;
- Completing and assembly of casing girders;
- Assembly of type III tower (temporary structures) for supporting the structures of western end wall;
- Preliminary erection and assembly of steel plating packages for casing, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 13,790.045 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13,284.82 tons

March 26, 2015
March 26, 2015
March 26, 2015
March 26, 2015
March 26, 2015
March 26, 2015
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Supplies to the site and completing main metal structures of the Arch;
- Assembly of metal structures of tilting panels TP-5-1, TP-5-2, TP-6;
- Assembly of bridging elements of main metal structures of western part of the Arch;
- Completing and assembly of casing girders;
- Assembly of type III tower (temporary structures) for supporting the structures of western end wall;
- Preliminary erection and assembly of steel plating packages for casing, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 13,767.045 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13,284.82 tons

March 19, 2015
March 19, 2015
March 19, 2015
March 19, 2015
March 19, 2015
March 19, 2015
 

Select the another date

Within the NSC Project at the construction site the following works are being performed:

- Supplies to the site and completing main metal structures of the Arch;
- Total assembly of metal structures of the Arch (including tilting panel TP-5-2);

- Assembly of filling elements of the main metal structures of the western part of the Arch;
- Completing and assembly of casing girders;
- Preliminary assembly of steel plating packages for casing, laying of 1 layer of Dachrock, assembly of EPDM membrane, assembly of bearing clips;
- Assembly of scaffolding and preparation of air ducts for assembling, assembling of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total –  13,732.59 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total –  13,284.82 tons

Select the another date

Within the NSC Project at the construction site the following works are being performed:

- Supplies to the site and completing main metal structures of the Arch;
- Total assembly of metal structures of the Arch (including tilting panel TP-6, TP-5-2);

- Assembly of filling elements of the main metal structures of the western part of the Arch;
- Completing and assembly of casing girders;
- Preliminary assembly of steel plating packages for casing, laying of 1 layer of Dachrock, assembly of EPDM membrane, assembly of bearing clips;
- Assembly of scaffolding and preparation of air ducts for assembling, assembling of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total –  13,696.995 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total –  13,284.82 tons

Select the another date

Within the NSC Project at the construction site the following works are being performed:

- Supplies to the site and completing main metal structures of the Arch;
- Total assembly of metal structures of the Arch (including tilting panel TP-6);

- Assembly of main metal structures of the western part of the Arch;
- Completing and assembly of casing girders;
- Preliminary assembly of steel plating packages for casing, laying of 1 layer of Dachrock, assembly of EPDM membrane, assembly of bearing clips;
- Assembly of scaffolding and preparation of air ducts for assembling, assembling of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – building wall arrangement (assembly of fittings and formwork);

- Arrangement of external and internal space of NSC (northern side):
   * End walls of the Arch;
   * Access gateway for fire brigades;
   * Walls of hinged bearing gallery;
   * Storm water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total –  13,555.009 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total –  13,272.22 tons

February 26, 2015
February 26, 2015
February 26, 2015
February 26, 2015
February 26, 2015
February 26, 2015