Spent Fuel Processing Facility (SFPF):

- Receipt  inspection of structures for mounting the IAEA cabinet in 107с.
- Finished backfilling of lead shot protective door SFP-SD-06.
- Marking of technological pipelines in the building of SFPF.

The following activities were also performed at the facility:

- Regular works on the construction site arrangement.
- Completing of executive & acceptance documentation according to the Contract.
- Development of test programs for technological units and systems.
- Development of a training program for Chornobyl Nuclear Power Plant personnel.
- Commissioning on main technological equipment and auxiliary.
- Finished Individual tests of the  ventilation and air conditioning system of the Gate House.
- Functional tests of crane SFP-CR-01 room. 119.
- Individual (Autonomous) tests of PCMS DWC Handling System, FT Handling System, SRW Management System.
- Individual tests of the security door SWP-SD-01.
- Finished Individual tests of the autonomous power supply system;
- Integrated testing of the Sewerage and Sewage Systems (Removing Remarks);
- Individual tests of the Cutting Machine SFA SFP-CS-205;
- Individual tests of the Removable Platforms SFP-PL-01;
- Finished Individual and Integrated testing of ISF-2 Fire Alarm and Personnel Evacuation Control System;
- Finished Individual and complex testing of the fire alarm warning system of Gate House;
- Finished Tests in accordance with Ukrainian Labor Service hoist MIS-CR-250, MIS-CR-15, KLE500GCL
- Individual Test of Canister Handling and Transport System CHT TD 02
- Functional tests of the crane SWP-CR-206 in room 403.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 189 persons were engaged in the works. 1 unit of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

 

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Preparatory work before the sealing anchors and the sealing membrane installation at the block V.

- Technological building and auxiliary facilities:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system
* Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

- Works on arranging the NSC internal and external space:

* Completion of fire and household water supply pipelines installation;
* Site improvement activity;
* Weather station establishment.

Other activity:

* Dismantling of the Turbine Hall light roof.

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

Completion of work on external and internal Arch lining arrangement;
Work to prepare and to test the main cranes system is underway;
* Preparatory work before the sealing anchors and the sealing membrane installation.

- Technological building and auxiliary facilities:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system
* Interior finishing of premises.

- Works on arranging the NSC internal and external space:

* Completion of fire and household water supply pipelines installation;
* Arrangement of roads and sidewalks within the local zone is close to completion — 98%;

* Site improvement activity;
* Weather station establishment.

Other activity:

* Dismantling of the Turbine Hall light roof.

October 26, 2017
October 26, 2017
October 26, 2017
October 26, 2017
October 26, 2017
October 26, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Work to prepare and to test the main cranes system is underway;

Completion of work on external and internal cladding arrangement;
* Arch ventilation system and auxiliary constructions (installation of supports, air ducts and ventilation equipment).

- Technological building and auxiliary facilities:

* Technological building (TB) — Installation of the cable ducts and cable laying, installation of gates. Installation of Fire Alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Preparation for RAW containers grippers testing using the 20 tons crane;
* Electrical Equipment Building (EEB) — installation of the Fire Alarm System, ventilation, installation of the electrical equipment. Work to install the hot water supply and heat supply systems is underway;
* Access Gateway for Fire brigades — installation of ventilation ducts, arrangement of the external facade, interior furnishing;
* Fire Extinguishing Pump Station — scaffolding dismantling;
* Diesel electric power station site — electrical equipment connection. Installation of a fueling station with a reserve tank of diesel fuel
* Sewage treatment facilities and pump station of storm water drainage — preparation for individual testing.

- Works on arranging the NSC internal and external space:

* Completion of fire and household water supply pipelines installation;
* Turbine Hall light roof dismantling;

* Construction of roads in Local zone — 100%.

 

Select another date

Spent Fuel Processing Facility (SFPF):

- The installation of the IAEA shield equipment continues.
- Backfilling of lead shot protective door SFP-SD-06.
- Re-install the valves of LRW pipelines.
- Marking of technological pipelines in the building of SFPF.
- Work continues on assembling the electrical cabinet of the crane CR-04. Launching of cable lines.
- Finished installation of the crosshead on the crane SFP-CR-01.
- Finished installation of local fire-extinguishing means in electrical cabinets.
- Work continues on fire protection of cable lines.

The following activities were also performed at the facility:

- Regular works on the construction site arrangement, such as: weeding of gravel coatings, grass cutting, irrigation, maintaining clean asphalt coverings.
- Compilation of executive and hand-over documents.
- Development of test programs for technological units and systems.
- Development of a training program for Chornobyl Nuclear Power Plant personnel.
- Commissioning on main technological equipment and auxiliary.
- Finished individual tests of baskets in the room 109B/111B.
- Finished functional tests of hoists MIS-CR 14, MIS-CR-06 SFP-CR-301, PWS-CR-301\1, PWS-CR-301\2.
- Individual (Autonomous) tests of PCMS DWC Handling System, FT Handling System, SRW Management System.
- Individual tests of the security door SWP-SD-01.
- Individual tests of the ISNT-2 autonomous power supply system;
- Individual tests of the system "Emergency lighting of SFPF";
- Integrated testing on PPS have been started;
- Individual and complex testing of outdoor lighting PSC;
- Integrated testing tests of RMS;
- Integrated testing of the Sewerage and Sewage Systems (Removing Remarks);
- Test Barrel monitoring station (CBC), Sub-Canberra.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 192 persons were engaged in the works. 1 unit of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.